Current DPW Projects

Pleasant Street Paving Operations - 2018 UPDATE

  • 2018 - 5/29 - 5/31 milling and 6/1 & 6/4 paving of trenches from 2017 water line work. Detours may be in place.
  • Contractor: Cardillo & Son, Inc.
  • Project: Connecting all residents along Pleasant Street to the 16" water line, resulting in increased fire-flow pressure, especially on Old Essex Rd, and improved ability to perform isolation in the future for any required repairs.
  • Information: Project COMPLETED 2017 - Paving 2018

Paving Repairs

  • Contractor: Brox Industries
  • Timeline: Throughout summer/fall 2017.
  • Project: PINE STREET - Repair and re-surface curb-to-curb from Pleasant Street to Central Street. Repair and patch from Pleasant Street towards Rt 128. COMPLETE - road markings to follow. 
  • Project: JERSEY LANE: Repair and resurface edge-to-edge. COMPLETE - road markings to follow.
  • Project: TUCKS POINT: Repair & re-surface - COMPLETE - road markings to follow.
  • Current Project: Boat Ramp - COMPLETE

Sewer Rehab Program

  • Contractor: RapidFlow - Mattuchio
  • Project: Clean lines and repair sewer pipes and manholes. Continuing efforts to reduce infiltration and inflow (I & I) of stormwater and groundwater into sewer system
  • Timeline: Information on next location to follow.
  • Information: Continuously moving operation
  • Current Project: Information to follow

North Street/School Street:

  • Contractor: RapidFlow - (Mattuchio)
  • Project: Replacement of Sewer Main
  • Timeline: Completion mid August
  • Information: Project COMPLETED 2017 - Paving 2018

Lincoln Street Water Line

  • Contractor: Cardillo & Son, Inc
  • Project: Replacement of water line on Lincoln St from Vine St to Summer St
  • Timeline: Work scheduled to be complete by start of school.
  • Information: Project COMPLETED - Paving 2018

Pump Stations

  • Contractor: Weston & Sampson
  • Project: Replacement of sewer pumps and installation of back-up power at the pumping stations on Ashland Ave, Rockwood Heights, Pine St and Old Essex Rd
  • Timeline: Starting September 2017
  • Information: Several locations - pump station work underway, this should not impact residents.