- Home
- Government
- Current Projects / Initiatives
- Project Dashboard
Project Dashboard
Updated December 2022
PROJECT | SUMMARY | CONTACT | STATUS |
---|---|---|---|
CURRENT | |||
Water Treatment Plant SCADA Upgrades | Waiting on equipment to be delivered so it can be implemented. | DPW Director -
Chuck Dam
978-526-1242 |
Anticipated completion in Late Fall 2022 |
Library ADA Bathroom Study | Study to find a suitable location in the library to add an ADA bathroom while trying to minimize impact to used spaces/services | DPW Director -
Chuck Dam
978-526-1242 |
Study will be completed Fall of 2022 |
Lincoln Street Well – PFAS monitoring and Treatment considerations |
Massachusetts DEP began testing requirements for PFAS in drinking water in fall of 2021. DPW is testing monthly and considering treatment options should they become warranted. |
DPW Director - Chuck Dam 978-526-1242 |
Monthly Testing- Ongoing Preliminary Design- Complete |
North Shore
Regional Compost
Facility
|
The Town voted to relocate the current compost site at the November 2019 Special Town Meeting. The DPW collected RFP's from interested compost service providers on June 10, 2021 and is ongoing. |
DPW Director -
Chuck Dam 978-526-1242
|
Black Earth is submitting permitting and design updates to DEP as well as DPW and Conservation Commission for review and approval. Construction is scheduled to start in Late Fall of 2022. |
2022 Water Main
(School Street,
Plum Hill) |
Cleaning of the water main on sections of School Street.
Installation of water main on Plum Hill from Hickory
Hill and connecting to Ancient County way to provide
redundancy for that area. |
DPW Director -
Chuck Dam
978-526-1242 |
Granese N Sons will be completing water main cleaning and lining on School Street in Fall of 2022, Plum Hill design is complete and construction Is contingent on additional funding. |
PLANNED | |||
Central St Culvert
Replacement
|
The Central St Culvert replacement will replace the existing 100+ year old stone culvert and replace with a new precast concrete arch culvert. This project will also remove the tide gate to improve the hydraulics of Central Pond/Sawmill brook | Town Engineer &
Facilities
Manager -Nate
Desrosiers 978-526-1242 |
In Design & Permitting Phase; Construction date is contingent upon award of FEMA Bric grant. At the earliest construction would begin in the Fall of 2023. |
Central Pond/Saw
Mill Brook
Restoration |
The Central Pond and Sawmill Brook stream walls will be repaired using natural shorelines and hard scape strategies. The mudflats will be planted with marsh reads to improve their resiliency. |
Town Engineer &
Facilities
Manager -Nate
Desrosiers 978-526-1242 |
Design and permitting have been completed; construction is contingent upon award of various grants the Town has applied for. At the earliest construction would begin in the Fall of 2023. |
Tappan St Water Main & Drainage Phase 1 |
Replacement of the water main on Tappan St. Rerouting of the storm water drainage system in the area of Tappan & Sea St. |
DPW Director -
Chuck Dam 978-526-1242 |
Design has been completed. Construction is contingent upon additional funding. |
DPW Relocation
Study |
Study to evaluate possible Town owned siting locations for a proposed new DPW. Existing DPW on Pleasant St is at its useful life. |
Town Engineer &
Facilities
Manager -Nate
Desrosiers 978-526-1242
|
Study is underway and will completed late fall 2022 or early winter 2023. |
Cemetery
Expansion
|
Currently a limited number of available cemetery plots for sale. Developing additional areas within the cemetery into plots that can be sold to residents. |
DPW Director -
Chuck Dam 978-526-1242 |
Expansion is under construction |
Downtown
Improvements
Project Phase 2 Study |
Study to explore continuing the DIPs phase 1 look/feel down to Pine Street past Town Hall, up to Washington St, and down to Tappan St from their existing limits. |
DPW Director -
Chuck Dam 978-526-1242 |
Study is underway and anticipated to be completed in fall 2022. |
RECENTLY COMPLETED | |||
2022 Chapter 90
Paving Town
Wide: Forest
St., Harold St. and Magnolia Ave.
(other streets TBD) |
Annual state funded Chapter 90 paving for roadway
and sidewalks. Final paving list TBD and based
upon other utility work completed. |
Town Engineer &
Facilities
Manager -Nate
Desrosiers
978-526-1242 |
Completed |
Guardrail Replacement | Raymond and Lincoln Streets will be done in May/June of 2022. | Town Engineer &
Facilities
Manager -Nate
Desrosiers
978-526-1242 |
Completed |
2021 Water Main
Replacement -
Forest St |
Work will commence in September and will go throughout
the fall. Roads will be open to traffic but use caution and
observe signage. All effected residents will receive
notification prior to any service interruptions. |
DPW Director -
Chuck Dam
978-526-1242 |
Completed |
Singing Beach Revetment Repairs and Stinky Beach Seawall Repairs | Reconstruction of sections of the Singing Beach revetment damaged during the 2018 winter storms and construction of a new section of seawall destroyed during the 2018 winter storms. | DPW Director -
Chuck Dam
978-526-1242 |
Completed |
WTP Replaced the Original Venturi Meters | Installed new mag meters which will improve the accuracy of our flow metering. | Town Engineer &
Facilities
Manager -Nate
Desrosiers
978-526-1242 |
Completed |
WTP & LSW Chemical Feed systems upgrades | Included replacement of chemical metering pumps/systems at the WTP and LSW WTP Flow Meter | Town Engineer &
Facilities
Manager -Nate
Desrosiers
978-526-1242 |
Completed |
WTP RAS System Replacement | Included replacement of pumps, valves, and piping associated with the return activated sludge system. | Town Engineer &
Facilities
Manager -Nate
Desrosiers
978-526-1242 |
Completed |
MAPC Green
Communities
Grant for Library
& Fire Dept.
Weatherization
Work |
Weather sealing of doors and windows at the library
and fire department. Construction
funded through
MAPC Green Communities grant |
Town Engineer &
Facilities
Manager -Nate
Desrosiers
978-526-1242 |
Completed |
Emergency
Services Radio
Upgrades
|
Complete upgrade of the Town’s Emergency Radio system used by Police, Fire, DPW, and Harbormaster to improve the range, radio clarity, and reduce weak signal zones in Town. |
Town Engineer &
Facilities
Manager -Nate
Desrosiers 978-526-1242 |
Completed Fall 2021 |
Seaside 1 Exterior Painting | Long term maintenance painting of the exterior siding and trim of the Seaside 1 building as existing paint was starting to fail. Project wasfunded by the CPC. |
Town Engineer &
Facilities
Manager -Nate
Desrosiers 978-526-1242 |
Completed Summer 2021 |
Town Hall HVAC | Installation of a VRF heat pump system for heating/ cooling Town Hall to replace the existing electric baseboard heating and window air conditioners. Also included replacement of the ventilation equipment and improved air filtration. |
Town Engineer &
Facilities
Manager -Nate
Desrosiers 978-526-1242
|
Completed Summer 2021 |
Harbor Loop
Sewer Lining |
CIPP (cured-in-place-pipe) lining of the harbor loop sewer, which was deteriorating and allowing salt water into the sewer system. Additional CIPP lining was completed on Bridge St, Central St, Church St, Beach St, Bennet St, along Sawmill Brook, and various other streets. |
Town Engineer &
Facilities
Manager -Nate
Desrosiers 978-526-1242
|
Completed Spring 2021 |
Round Pond Well #1 Cleaning & Redevelopment |
Long term maintenance of the Round Pond well which included redevelopment of the well to regain lost capacity, installation of new well pump, and cleaning of the well. |
DPW Director -
Chuck Dam 978-526-1242 |
Completed Spring 2021 |
Complete Streets | Three intersections in town are being redesigned to improve traffic flow, pedestrian safety and to better accommodate those with mobility challenges. |
DPW Director -
Chuck Dam 978-526-1242
|
School/Central and Union/Beach
intersections completed Spring
2020
|
WTP Sprinkler System Replacement |
Replacement of the fire protection sprinkler system at the Water treatment plant which also included nitrogen charging system for “dry” portions to prevent future failures due to leaks/cold weather. |
DPW Director -
Chuck Dam 978-526-1242
|
Completed Spring 2020 |
Town Common | Reconstruction of the Town Common in front of Town Hall. Improvements included new permeable paver walkways and ramp, trees, sod, HC parking, and incorporation of the new Veterans’ Memorial. |
Town Engineer &
Facilities
Manager -Nate
Desrosiers 978-526-1242 |
Completed Fall 2020 |
WTP, WWTP, DPW HVAC Repairs/Upgrades
|
Repairs to the existing heating systems in the WTP, DPW, WWTP. Installation of hazardous gas detection and ventilation at the DPW. |
DPW Director -
Chuck Dam 978-526-1242 |
Completed Fall 2020 |
2020 Water Main
Replacement
|
Replacement of water main on Boardman Ave from Bridge St to Harbor St. |
DPW Director -
Chuck Dam 978-526-1242 |
Completed Fall 2020 |
WTP Sodium Fluoride Replacement
|
Replacement of the original hydrofluorosilicic acid chemical feed system with a sodium fluoride dry chemical feed system, as approved by DEP, to fluoridate the drinking water. |
DPW Director -
Chuck Dam 978-526-1242 |
Completed Fall 2019 |
PROJECT | SUMMARY | CONTACT | STATUS |
---|---|---|---|
Tucks Point Rotunda Pile/Pier Replacement Design | The Town received a grant to hire an engineering firm to present options for undertaking the needed rebuilding of the support structures to the Tuck’s Point Rotunda. | Bion Pike
Harbormaster
978-473-2520 |
Design to begin in FY23 |
Floats for Fisherman | Creation of a docking facility for commercial fishermen at the head of the harbor. Facility will span between Masconomo and Reed parks with finger slips for the vessels. |
Bion Pike
Harbormaster 978-473-2520 |
Permitting and engineering underway. FOTH Engineering |
Harbor Dredging | Maintenance of channel and mooring fields to preserve safe and adequate access to boaters |
Bion Pike
Harbormaster 978-473-2520
|
Permitting and engineering underway. FOTH Engineering |
Tuck’s Point
Ramp/Floats |
Installation of a fully permitted and compliant docking facility at the Rotunda. Permitting and engineering is complete and final license off for signature by the Governor. |
Bion Pike
Harbormaster 978-473-2520 |
Completed |
Phase II Floats Reed Park | Two grants submitted (US Fish and Wildlife - Seaport Economic Council) to complete the Reed Park docking facility for transient vessels Facility will span to the drawbridge with water and electricity available. | Bion Pike
Harbormaster
978-473-2520 |
Grants submitted |
PROJECT | SUMMARY | CONTACT | STATUS |
---|---|---|---|
MHA/MAHT Housing Project | The Manchester Housing Authority (MHA) and the Manchester Affordable Housing Trust (MAHT) have been working on a plan to improve the existing 84 MHA public housing units and create additional affordable housing at Newport Park, the Plains and Loading Place Road. To support the redevelopment, the project would also create housing on the DPW site (if approved by the Town). Following completion of a Feasibility Study for the proposed project, the MAHA and MAHT have issued a request for proposals to secure a Development Partner. Proposals are due October 24th. |
Betsy Ware, Interim Town Planner |
Learn More |
PROJECT | SUMMARY | CONTACT | STATUS |
---|---|---|---|
Athletic Field Master Plan | Weston and Sampson, an engineering firm, have surveyed our recreational facilities and their users and have compiled the data into documents for review and consideration. | Parks & Rec
Director –
Cheryl Marshall 978-526-2019 |
Learn More |
Pine St Field - Old Burn Dump |
Funding for engineering was approved at Fall Town Meeting. | Parks & Rec
Director –
Cheryl Marshall 978-526-2019
|
In Design Phase (Ongoing) |
Fields - Sweeney Park | Engineering has started for a full-sized turf field to accommodate soccer, field hockey, lacrosse, flag football and softball/baseball. |
Parks & Rec
Director –
Cheryl Marshall 978-526-2019 |
In Design Phase (Ongoing) |
Pickleball Courts
at Old Skate Park |
Plan to put out to bid in January for a spring project. | Parks & Rec
Director –
Cheryl Marshall 978-526-2019 |
Project Completed - July, 2022 |
PROJECT | SUMMARY | CONTACT | STATUS |
---|---|---|---|
Limited Commercial District Study |
The Limited Commercial District Study has identified a mix and density of uses for a mixed-use neighborhood in the LCD and is creating draft zoning regulations and design guidelines that would allow the site to be built out. As with any zoning change, the overlay district regulations would need Town Meeting approval. |
Town Planner |
Completed Learn More |
Western Woods | The Town is exploring options for preserving the large undeveloped wooded area west of Pine Street. The Town has received a state grant and has hired a professional forester to inventory, map and assess lands within the Western Woods and develop recommendations for maintenance and management. |
Town Planner | Forester’s report to be completed by the end of 2022. |
Master Plan | The Planning Board adopted the Manchester Comprehensive Master Plan in 2019 and is working to implement its recommendations. Key initiatives include updating the Town's Zoning Bylaws, supporting more diversified housing and preserving, protecting and managing the Town's open spaces. | Town Planner | Learn More |
Zoning Recodification and Update |
The Planning Board, ZBA Chair, Building Inspector and Town Planner have been working with Attorney Mark Bobrowski for over three years to propose changes for updating and improving the Town's Zoning Bylaws. Reorganization and other changes have been approved in recent Town Meetings, further changes are being recommended to the voters at the 2022 Special Town Meeting in November. | Town Planner | Learn More |
Local Rapid Recovery Plan | In mid-Nov, the Board of Selectmen voted to move ahead with two priority projects that were recommended in the study. These include Improved Placemaking and an Off-Season Event Series. Also, as part of these plan recommendations, the Board of Selectmen approved a study to further explore additional restrooms in town that may be part of a new Harbormaster’s Office. The Town continues to seek grant funding for these projects. |
Town Planner | Learn More |
Downtown Parking Study | The Town is undertaking a downtown parking study to identify the parking needs of the downtown and provide information on parking capacity, occupancy, and duration, as well as recommend ways to manage the existing parking supply more effectively. This study will also identify ways the Town could align new zoning regulations downtown with the aim of boosting residential and commercial vitality. | Town Planner | On going through 2022 |
PROJECT | SUMMARY | CONTACT | STATUS |
---|---|---|---|
Public Safety Dispatch | The Select Board voted to move Public Safety Dispatch operations from in-house to the North Shore Regional 911 Center in June 2022. The transition will take approximately one year to complete. | Greg Federspiel
Town
Administrator 978-526-2000 |
Learn More |
PROJECT | SUMMARY | CONTACT | STATUS |
---|---|---|---|
40B Affordable Housing Proposal |
The ZBA issued a denial on the 40B comprehensive permit application by SLV. SLV appealed the decision in September 2022. | Greg Federspiel, Town Administrator | ZBA issued denial - August 2022. Currently in MA appeals court. |
PROJECT | SUMMARY | CONTACT | STATUS |
---|---|---|---|
Policy Review | Review and update of Policies that have been adopted by the Selectmen since the late 1970’s. |
Greg Federspiel
Town
Administrator 978-526-2000
|
Reviews Ongoing |
Water Resource
Protection Efforts |
Review and update the Water Resources Protection Plan developed in the early 1990’s; Working in Conjunction with the Conservation Commission and other boards and committees. |
Greg Federspiel
Town
Administrator 978-526-2000
|
Completed - Water Resource Protection Task Force was formed - December, 2021 Learn More |